MHPS' Unit 2 of the "Jawa-2" Natural-gas-fired Power Plant Goes into Operation
Completes Construction Ahead of Schedule, Complementing Early Start-up of Unit 1 in June

- Second unit of 880 MW GTCC power generation facility launched as a simple cycle system
- Power supply achieved ahead of 2018 Asian Games held in August 2018

YOKOHAMA, Japan, Aug 7, 2018 - (JCN Newswire) - Mitsubishi Hitachi Power Systems, Ltd. (MHPS) has completed construction of its Unit 2 Gas Turbine Combined Cycle System at the Tanjung Priok Power Plant, a natural-gas-fired power generation facility being built on Java Island in Indonesia. Construction was completed ahead of schedule and went into operation on July 18. Under the "Jawa-2 Project," PT. PLN (Persero), Indonesia's state owned electricity provider, plans to build an 880 megawatt (MW) plant comprising of two gas turbine combined cycle (GTCC) power generation systems. Unit 1 initially went into operation as a simple gas turbine system this June with output nearing 300 MW, and now Unit 2 has joined to produce equivalent wattage. Both units were finished ahead of schedule.

A ceremony was held at the facility on August 1 to mark the launch of operation of Unit 2. Attending as PLN's representative was Director W.S. Haryanto, who oversees company operations in the provinces of West Java, where the Jawa-2 Project is underway. Also in attendance was MHPS Senior Vice President, Takashi Tozawa.

"We greatly appreciate the contribution the Contractor has made to inaugurate the new plant's commercial operation ahead of schedule, and prior to the 18th Asian Games," Mr. Haryanto said. "The Jawa-2 project is important for both the competition and the Java power network."

Jawa-2 is a project to construct GTCC power generating facilities in Tanjung Priok, a port city approximately 10 km northeast of central Jakarta. The full-turnkey order for the power plant was received by MHPS in partnership with Mitsubishi Corporation and PT. Wasa Mitra Engineering, a local construction and engineering firm. MHPS is responsible for providing two M701F gas turbines as well as two exhaust heat recovery boilers, one steam turbine, and auxiliary equipment. Mitsubishi Electric Corporation supplied the generators. The launch of operations as a GTCC system, generating power by gas turbine and by a steam turbine utilizing recovered exhaust heat, is slated for 2019.

MHPS holds the top market share for large gas turbines in Indonesia, and with the latest system start-up, the total generation capacity of equipment supplied by MHPS for power producers reached 12 GW. MHPS has supported Indonesia's power supply for roughly 50 years, and the company is engaging its total resources in the Jawa-2 Project to enhance customer satisfaction even further.

Going forward, MHPS will aim to further enhance its presence within the Indonesian power market. Through expanded adoption of high-efficiency power generation facilities, the company will continue to promote use of low-carbon energies as a way of contributing to protection of the global environment.


About Mitsubishi Hitachi Power Systems, Ltd.

Mitsubishi Hitachi Power Systems, Ltd. (MHPS) was formed on February 1 2014, integrating the thermal power generation systems businesses of Mitsubishi Heavy Industries, Ltd. (MHI) and Hitachi, Ltd. in a quest to further enhance their social response capabilities in all respects. These include the technological strength to create new products of outstanding quality and reliability, the comprehensive strength in engineering to oversee projects in regions across the globe, and finely honed sales and after-sale servicing capabilities. MHPS aims to come out a winner in global competition and achieve a solid position as a world leader in thermal power generation systems and environmental technologies. For more information, please visit www.mhps.com.

Contact:
Joseph Hood, PR Manager
Mitsubishi Heavy Industries, Ltd.
Email: [email protected]
Tel: +81-(0)3-6716-2168
Fax: +81-(0)3-6716-5860


Aug 7, 2018 10:46 HKT/SGT
Source: Mitsubishi Hitachi Power Systems, Ltd.

Topic: Press release summary
Sectors: Energy
http://www.acnnewswire.com
From the Asia Corporate News Network


Copyright © 2018 ACN Newswire. All rights reserved. A division of Asia Corporate News Network.


Multimedia
Jawa-2 Project
View Image
 

Mitsubishi Hitachi Power Systems, Ltd.
Oct 12, 2018 17:56 HKT/SGT
Operations Begun at China's Sanmen Nuclear Power Plant Unit 1
Oct 12, 2018 12:09 HKT/SGT
MHPS Opens New Office in Doha
Aug 31, 2018 12:09 HKT/SGT
MHPS to Transfer Entire Industrial-use Non-Reheat Thermal Power Facilities Business in Japan to MHPS-IDS
Aug 29, 2018 16:30 HKT/SGT
MHPS Signs MOU with Dongfang Electric and Sichuan Provincial Investment Group on a State-of-the-Art Natural-Gas-Fired Power Generation Facility
Aug 28, 2018 16:41 HKT/SGT
Mitsubishi Shipbuilding and MHPS Sign Collaboration Framework Agreement with CHI Dalian on Manufacturing and Marketing of Rectangular SOx Scrubbers
Aug 21, 2018 10:34 HKT/SGT
Soma Energy Park Begins Using MHPS-TOMONI at Pulverized Coal-Biomass Power Plant
Aug 9, 2018 12:09 HKT/SGT
MHPS to Participate in Vietnam's Nghi Son-2 Thermal Power Project
Aug 8, 2018 13:28 HKT/SGT
MHPS Continues Global Turbine Leadership
July 13, 2018 14:51 HKT/SGT
TEPCO Fuel and Power & MHPS Launch Digital Solution Service to Improve Asset Value of Clean Coal Power Plants
July 4, 2018 10:48 HKT/SGT
MHPS Receives Order for 7-Year Long-Term Parts Management and Services for Germencik Geothermal Power Plant in Turkey
More news >>
 News Alerts
Copyright © 2018 ACN Newswire - Asia Corporate News Network
Home | About us | Services | Partners | Events | Login | Contact us | Privacy Policy | Terms of Use | RSS
US: +1 800 291 0906 | Beijing: +86 10 8405 3688 | Hong Kong: +852 2217 2912 | Singapore: +65 6304 8926 | Tokyo: +81 3 6721 7212

Connect With us: